The Quad, Norwich
Case Study: The Quad, Student Residences, Norwich
Main Contractor: HG Construction
Design And Built Contract: Excelsior Services (Student Accommodation) Ltd
Project Value: £2.35 Million
Duration: 40 Weeks
248 Bedroom student accommodation made up of a mixture of cluster bedrooms with shared kitchen facilities and studios with self-contained bedrooms and kitchens.
- Serviced by a central plant room consisting of gas fired boilers, CHP, water storage tank and full BMS controls
- Heating was an electric system with panel heaters in each bedroom, kitchen and communal areas.
- Full domestic hot and cold water systems
- Full data network with wifi
- Extract ventilation in each studio and cluster
- Full L1 fire alarm system
- Disabled alarm and refuge
- Full external lighting
- Full CCTV coverage internal and external
- Electrical services are provided via a substation, site wide LV distribution and all internal/external lighting and power
- Key fob access system
- Full sprinkler system